Background


According to
Schnabel Engineering:


In
2005, settlement and lateral movement of the North Plaza and the Ashlar Seawall
prompted the National Park Service (NPS) to close a portion of the Jefferson
Memorial due to public safety concerns. Schnabel was commissioned by NPS to
analyze the problem and develop a repair strategy. [They] conducted an extended
settlement study to determine the cause of the seawall and North Plaza
movements and the rate of settlement. The problem was in large part due to the
foundation timber piles of the seawall not extending to bedrock.


Schnabel
conducted a value analysis with NPS to determine the best remedy. The selected
option involved demolition and then reconstruction of the seawall on
48-inch-diameter caissons and 18-inch-diameter steel pipe piles. This $13.5
million project was one of the first in Washington, DC to be funded by the
American Recovery and Reinvestment Act of 2009. The project received an ASCE
2012 Project of the Year Award from the National Capital Section.


In 2016, I
filed a FOIA request to see documentation relating to the project. Below, you
will find a breakdown of the records that came in from the National Park
Service (NPS).


Declassified Documents


 FOIA
Response, dated November 10, 2016
[3 Pages, 0.4MB]


 JEFM_808_106595_0440pg.pdf
CONTRACT
#1443C2000040800 REPAIR AND CONTROL SETTLEMENT AT JEFFERSON MEMORIAL SEAWALL,
NORTH PLAZA AND TRANSITION AREAS – PMIS NO 128232 – SUPPLEMENTAL DOCUMENTS
 [441
Pages, 25.5MB]


 JEFM_808_117504_0001_of_0116.pdf
Repair and Control
Settlement at Thomas Jefferson Memorial Seawall, North Plaza, and Transition
Areas NAMA 128232
 [116 Pages, 13.7MB]


 JEFM_808_128922_A.pdf
PROJECT SITE
 [3
Pages, 10.4MB]


 JEFM_808_25005_A_Redacted.pdf
–  AS-BUILT PROJECT
DRAWINGS ON FIELD SET BY CLARK CONSTRUCTION RECORD BASED (SEPTEMBER 2011)
 [58
Pages, 74.5MB]


 JEFM_808_25005_Redacted.pdf
–  EMERGENCY
REPAIRS FOR SETTLEMENT AT JEFFERSON MEMORIAL SEAWALL 
[54
Pages, 17.8MB]


 JEFM_808_C5_1.pdf
– Investigation of Settlement and Upheaval at the Jefferson Memorial National
Mall & Memorial Parks, January 30, 2008
 [315 Pages, 33.9MB]


 JEFM_808_C5_2.pdf
– Investigation of Settlement and Upheaval at the Jefferson Memorial National
Mall & Memorial Parks, January 30, 2008, Class C Estimate – Final
 [13
Pages, 0.3MB]


 NAMA_802_25002_A_0001_of_0050.pdf
–  EMERGENCY
REPAIRS FOR SETTLEMENT AT JEFFERSON MEMORIAL SEAWALL 
[50
Pages, 8.6MB]



 NAMA_802_D69_0001_of_0072_F808C6.pdf
CONTRACT
#1443C2000040800 REPAIR AND CONTROL SETTLEMENT AT JEFFERSON MEMORIAL SEAWALL,
NORTH PLAZA AND TRANSITION AREAS – PMIS NO 128232 – FINAL PREDESIGN DOCUMENTS
 [72